The Hibbits Kitchen
This has been a great project to work on. Because of our task based work list, a smooth and efficient project schedule allowed us to finish ahead of our estimated completion time. This entire kitchen project was scheduled to take five weeks. MAB Home Services took this job from demo to completion in just 17 working days. Please take some time to view the project timeline and the before and after pictures below.
Contract signed February 14, 2005
Design, Drawings and Planning: March / April 2005
Job started on May 2 2005
|
Days
|
Date
|
Job Progress
|
|
1
|
5/2
|
demolition and removal of old kitchen and flooring
|
|
2
|
5/3
|
rough electrical work and HVAC
|
|
3
|
5/4
|
paint walls
|
|
4
|
5/5
|
install new wood floor
|
|
5
|
5/6
|
new cabinets delivered
|
|
6
|
5/9
|
start cabinet install
|
|
7
|
5/10
|
complete cabinet install
|
|
8
|
5/11
|
template counter top
|
|
9
|
5/12
|
install appliances
|
|
10
|
5/13
|
install appliances
|
|
11
|
5/16
|
miscellaneous trim
|
|
12
|
5/17
|
miscellaneous fittings and adjustments
|
|
13
|
5/18
|
install door pulls and sink
|
|
14
|
5/19
|
install counter tops
|
|
15
|
5/20
|
install tile backsplash
|
|
16
|
5/23
|
final trim and plumbing
|
|
17
|
5/24
|
final electric / clean up / project complete
|